[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982020":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982020,710,2,"多选题","工作分解结构的作用有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","清晰梳理工程建设项目或政府采购活动的全貌",true,{"key":16,"text":17,"correct":14},"B","清晰地表示各项目工作之间的相互关系",{"key":19,"text":20,"correct":21},"C","有助于落实招标采购合同管理体系",false,{"key":23,"text":24,"correct":14},"D","有助于准确界定项目工作的内容和范围",{"key":26,"text":27,"correct":14},"E","有助于招标人确定项目管理人员和有效地管理项目","ABDE","工作分解结构有如下作用：①清晰梳理工程建设项目或政府采购活动的全貌，详细说明为完成项目所必须完成的所有工作，为计划、成本、进度和质量控制奠定共同基础，是确定项目进度控制的基准。②清晰地表示各项目工作之间的相互关系，对各独立的工作单元，进行有针对性的成本、进度和资源需求量的估算，提高估算的准确度。③有助于准确界定项目工作的内容和范围，也有助于招标人确定项目管理人员和有效地管理项目。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]