[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982018":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982018,710,2,"多选题","下列关于招标采购合同规划与项目管理方案的关系的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对项目进行工作分解以招标采购合同规划为基础",false,{"key":16,"text":17,"correct":18},"B","项目管理方案应建立在对项目进行工作分解的基础上",true,{"key":20,"text":21,"correct":14},"C","招标采购合同规划是项目管理方案内容的基础条件",{"key":23,"text":24,"correct":18},"D","招标采购合同规划应建立在对项目进行工作分解的基础上",{"key":26,"text":27,"correct":18},"E","招标采购合同规划直接影响项目管理方案目标的实现","BDE","招标采购合同规划是项目管理方案的重要组成部分。项目管理方案与招标采购合同规划既有联系又有区别：①项目管理方案和招标采购合同规划均应建立在对项目进行工作分解的基础上；②项目管理方案内容是招标采购合同规划的基础条件；③招标采购合同规划直接影响项目管理方案目标的实现。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]