[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982004,710,2,"多选题","招标采购合同规划的最终成果文件应包括的内容有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目概况",true,{"key":16,"text":17,"correct":18},"B","后期合同规划",false,{"key":20,"text":21,"correct":14},"C","合同要素计划分配书",{"key":23,"text":24,"correct":14},"D","合同订立顺序及条件建议书",{"key":26,"text":27,"correct":14},"E","成果文件的使用条件及使用提示","ACDE","招标采购合同规划的最终成果文件应至少包括六个部分内容：①项目概况；②初步合同规划；③项目合同结构与体系；④合同要素计划分配书；⑤合同订立顺序及条件建议书；⑥成果文件的使用条件及使用提示。此外，招标采购合同规划的各个阶段成果都应具有相应的内容和形式要求，招标人应将招标采购合同规划的阶段成果实行档案化管理，以保证档案资料的真实性、完整性以及可追溯性。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]