[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},981998,710,2,"多选题","关于工作单元与合同单元的关系，下列理解正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","具备独立交易条件和可以独立作为合同内容的最小工作单元，即为最小合同单元",true,{"key":16,"text":17,"correct":14},"B","不能独立交易、不能独立作为合同内容的最小工作单元，应与其他最小工作单元一起构成最小合同单元",{"key":19,"text":20,"correct":14},"C","确定最小工作单元和最小合同单元是确定招标合同单元的前提",{"key":22,"text":23,"correct":24},"D","合理确定最小工作单元和最小合同单元是招标采购合同规划的根本目的",false,{"key":26,"text":27,"correct":14},"E","合理确定招标合同单元是招标采购合同规划的根本目的","ABCE","A项，具备独立交易条件和可以独立作为合同内容的最小工作单元，即为最小合同单元；B项，不能独立交易、不能独立作为合同内容的最小工作单元，应与其他最小工作单元一起，构成最小合同单元；CDE三项，确定最小工作单元和最小合同单元是确定招标合同单元的前提，合理确定招标合同单元是招标采购合同规划的根本目的。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]