[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981995":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},981995,710,2,"多选题","下列关于招标采购合同重点要素管理的说法中，错误的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同变更条款中涉及价款管理",false,{"key":16,"text":17,"correct":18},"B","作为质量管理的要点，质量修复责任和赔偿责任总是会出现",true,{"key":20,"text":21,"correct":18},"C","合同总体进度管理可以采取定性数据进行管理",{"key":23,"text":24,"correct":14},"D","安全管理是实现合同投资管理、质量管理、进度管理的保障",{"key":26,"text":27,"correct":14},"E","质量要求管理和质量标准管理是质量管理的核心","BC","B项，质量要求管理和质量标准管理是质量管理的核心，质量修复责任和质量赔偿责任只有在供应商无法满足质量要求的情形下才有可能出现；C项，合同总体进度管理，是指对合同所需达到的总体进度目标的管理，应采取定量数据进行管理。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]