[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981994":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},981994,710,2,"多选题","合同目标分析应遵循的原则有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同目标的不确定性",false,{"key":16,"text":17,"correct":18},"B","合同目标的可衡量性",true,{"key":20,"text":21,"correct":18},"C","合同目标的系统性",{"key":23,"text":24,"correct":18},"D","合同目标的可实现性",{"key":26,"text":27,"correct":14},"E","合同目标的局部性","BCD","合同目标分析应遵循以下原则：①合同目标的确定性，并有明确具体的结果或成果要求；②合同目标的可衡量性，包括质量、数量、时间、成本等指标；③合同目标的系统性，即阶段合同目标之间应相互衔接构成有机统一体；④合同目标的可实现性，即合同目标的实现既有挑战性又有现实的实现可能；⑤合同目标的整体性，合同目标应围绕项目整体目标和招标人经营目标开展。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]