[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981993":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},981993,710,2,"多选题","合同结构分解作为招标采购合同规划的基本工作，招标师在创建项目合同结构体系时，应注意()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同结构分解需以工作分解结构为前提",false,{"key":16,"text":17,"correct":14},"B","合同结构分解应以分析项目总体需求为基础",{"key":19,"text":20,"correct":21},"C","合同结构分解应对项目具体内容进行详细的陈述，并保证特定单份合同的唯一性和特定性",true,{"key":23,"text":24,"correct":21},"D","合同结构分解应注重历史数据的收集、分析和归纳",{"key":26,"text":27,"correct":21},"E","合同结构分解应合理分配履行主体的权利义务","CDE","合同结构分解作为招标采购合同规划的基本工作，招标师在创建项目合同结构体系时，应注意以下几点：①合同结构分解需以分析项目总体需求为前提；②合同结构分解应以工作分解结构为基础；③合同结构分解应对项目具体内容进行详细的陈述，并保证特定单份合同的唯一性和特定性；④合同结构分解应注重历史数据的收集、分析和归纳；⑤合同结构分解应合理分配履行主体的权利义务；⑥合同结构分解应结合项目实施的限制条件；⑦合同结构分解需对不确定因素进行必要假设；⑧确定招标合同单元时应易于高效管理。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购合同管理-(原案例分析)","建筑工程",0]