[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981957":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},981957,710,1,"单选题","下列各项中，不属于合同实施情况偏差分析内容的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同实施趋向预测",false,{"key":16,"text":17,"correct":14},"B","合同执行差异的原因分析",{"key":19,"text":20,"correct":14},"C","合同偏差责任分析",{"key":22,"text":23,"correct":24},"D","合同偏差调整",true,"合同实施情况偏差分析，是指在合同实施情况追踪的基础上，评价合同实施情况及其偏差，预测偏差的影响及发展的趋势，并分析偏差产生的原因，以便对该偏差采取调整措施。合同实施情况偏差分析包括：①合同执行差异的原因分析；②合同偏差责任分析；③合同实施趋向预测等。D项属于合同偏差处理，不属于合同实施情况偏差分析。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]