[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981938":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981938,710,1,"单选题","下列关于争议评审的说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在争议发生后，争议评审组由发包人和承包人协商成立",true,{"key":16,"text":17,"correct":18},"B","采取争议评审，发包人和承包人应当在开工日后的14天内协商成立争议评审组",false,{"key":20,"text":21,"correct":18},"C","争议评审组的人员构成无特殊要求",{"key":23,"text":24,"correct":18},"D","评审意见对发包人和承包人具有法定拘束力，当事人不得再寻求诉讼或者仲裁","BC项，采用争议评审的，发包人和承包人应在开工日后的28天内或在争议发生后协商成立争议评审组。争议评审组由有合同管理和工程实践经验的专家组成。D项，发包人和承包人接受评审意见的，由监理人根据评审意见拟定执行协议，经争议双方签字后作为合同的补充文件，并遵照执行；发包人或承包人不接受评审意见，并要求提交仲裁或提起诉讼的，应在收到评审意见后的14天内将仲裁或起诉意向书面通知另一方，并抄送监理人，但在仲裁或诉讼结束前应暂按总监理工程师的确定执行。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]