[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981885,710,1,"单选题","()是实施特许经营项目的纲领性文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目经济技术",false,{"key":16,"text":17,"correct":18},"B","项目实施方案",true,{"key":20,"text":21,"correct":14},"C","政府承诺条款",{"key":23,"text":24,"correct":14},"D","合同文本","合同准备及签约管理包括项目经济技术论证、项目实施方案编制、合同授予方式选择、特许经营者条件设置以及合同签约管理。其中，项目实施方案是实施特许经营项目的纲领性文件。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]