[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981865,710,1,"单选题","工程设计咨询工作进行的时间是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在设计文件审查、施工图交付施工之前",true,{"key":16,"text":17,"correct":18},"B","在建设项目开展前期立项工作时",false,{"key":20,"text":21,"correct":18},"C","在工程建设的全过程中",{"key":23,"text":24,"correct":18},"D","在对建设项目投资、工程造价的确定与控制等提供专业咨询服务时","工程设计咨询工作一般应在设计文件审查、施工图交付施工之前进行。B项是项目前期咨询工作进行的时间；C项是项目管理咨询工作进行的时间；D项是工程造价咨询工作进行的时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]