[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981862":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981862,710,1,"单选题","下列关于设计咨询合同重点条款的说法中，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计咨询人必须公正诚信地从事咨询工作，对咨询报告的客观性和准确性负责",false,{"key":16,"text":17,"correct":14},"B","委托人不得授意咨询人提出不真实的咨询意见",{"key":19,"text":20,"correct":21},"C","检查可行性研究报告批复意见执行情况是可行性研究阶段设计咨询合同的主要服务内容",true,{"key":23,"text":24,"correct":14},"D","设计文件中违反国家有关法律、法规、政策和强制性技术标准的，设计咨询人负责提出改正意见","在初步设计阶段，设计咨询合同主要服务内容包括：①检查可行性研究报告批复意见执行情况；②局部方案比选；③特殊工点技术措施；④工程数量等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]