[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981706,710,1,"单选题","下列关于设计人主要工作的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计人应当完成合同约定的工程设计任务，以及专用合同条款约定的义务",false,{"key":16,"text":17,"correct":18},"B","设计人需要更换项目负责人的，应在专用合同条款约定的期限内提前书面通知发包人，并征得发包人口头同意",true,{"key":20,"text":21,"correct":14},"C","设计人应在接到开始设计通知后7天内，向发包人提交设计人项目管理机构及人员安排的报告",{"key":23,"text":24,"correct":14},"D","设计人不得将其承包的全部工程设计转包给第三人，或将其承包的全部工程设计肢解后以分包的名义转包给第三人","B项，设计人需要更换项目负责人的，应在专用合同条款约定的期限内提前书面通知发包人，并征得发包人书面同意。未经发包人书面同意，设计人不得擅自更换项目负责人。设计人擅自更换项目负责人的，应按照专用合同条款的约定承担违约责任。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]