[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981697,710,1,"单选题","关于变更管理，下列说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提出变更的，应通过监理人向发包人发出变更指示，该变更指示应指明变更事项的工程范围和变更的内容",true,{"key":16,"text":17,"correct":18},"B","监理人提出变更建议的，因尚需获得发包人的批准，该变更建议需要提交书面形式",false,{"key":20,"text":21,"correct":18},"C","监理人的变更建议是具体和可操作的，应当具体到图纸、标准、范围、数量、价格等方面，尤其应该测算对合同工期变化的影响",{"key":23,"text":24,"correct":18},"D","发包人收到承包人不能执行变更指令的理由后，应当审慎考虑，如承包人的理由能够成立的，发包人应通过监理人通知承包人停止执行该变更指令","A项，关于变更的提出，发包人提出变更的，应通过监理人向承包人发出变更指示，该变更指示应指明变更事项的工程范围和变更的内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]