[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981696,710,1,"单选题","关于变更程序，下列说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变更程序按照提出变更、变更指示、变更估价执行",true,{"key":16,"text":17,"correct":18},"B","发包人同意承包人根据变更意向书要求提交变更实施方案的，由监理人按合同约定发出变更指示",false,{"key":20,"text":21,"correct":18},"C","监理人应按照合同约定和合同当事人商定或确定变更价格",{"key":23,"text":24,"correct":18},"D","变更指示只能由监理人发出","变更程序按照提出变更、变更估价、变更指示执行：①变更的提出。发包人同意承包人根据变更意向书要求提交变更实施方案的，由监理人按合同约定发出变更指示。②变更的估价。监理人应按照合同约定和合同当事人商定或确定变更价格。③变更指示。变更指示只能由监理人发出。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]