[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981693,710,1,"单选题","在履行合同过程中，()可按照合同约定的变更程序向承包人作出有关发包人要求改变的变更指示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","监理人",true,{"key":20,"text":21,"correct":14},"C","项目经理",{"key":23,"text":24,"correct":14},"D","总承包商","在履行合同过程中，经发包人同意，监理人可按照合同约定的变更程序向承包人作出有关发包人要求改变的变更指示，承包人应遵照执行。变更应在相应内容实施前提出，否则发包人应承担承包人损失。没有监理人的变更指示，承包人不得擅自变。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]