[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981683,710,1,"单选题","关于最终结清条款，下列说法错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最终结清条款包括最终结清申请单、最终结清证书和支付时间",false,{"key":16,"text":17,"correct":14},"B","缺陷责任期终止证书签发后，承包人可按专用合同条款约定的份数和期限向监理人提交最终结清申请单，并提供相关证明材料",{"key":19,"text":20,"correct":21},"C","承包人对发包人签认的最终结清证书有异议的，不按争议条款的约定执行",true,{"key":23,"text":24,"correct":14},"D","发包人对最终结清申请单内容有异议的，有权要求承包人进行修正和提供补充资料，由承包人向监理人提交修正后的最终结清申请单","C项，最终结清条款包括最终结清申请单、最终结清证书和支付时间。其中，在最终清洁证书方面，如果承包人对发包人签认的最终结清证书有异议的，按争议条款的约定执行。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]