[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981682,710,1,"单选题","与《2007版标准文件》不同，《2013版施工合同》通用条款中增加了发包人的索赔期限为_____，发包人未在索赔事件发生后______内通过监理人向承包人提出索赔意向通知书的，丧失要求赔付金额和（或）延长缺陷责任期的权利。()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","28天；30天",false,{"key":16,"text":17,"correct":14},"B","30天；30天",{"key":19,"text":20,"correct":21},"C","28天；28天",true,{"key":23,"text":24,"correct":14},"D","25天；25天","《2013版施工合同》完善了逾期索赔失权制度。与《2007版标准文件》不同的是，《2013版施工合同》通用条款中增加了发包人的索赔期限为28天，发包人未在索赔事件发生后28天内通过监理人向承包人提出索赔意向通知书的，丧失要求赔付金额和（或）延长缺陷责任期的权利。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]