[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981676,710,1,"单选题","关于索赔条款，下列说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同中的索赔条款一般包括索赔情形、索赔期限及索赔方式",false,{"key":16,"text":17,"correct":18},"B","承包人未能在知道或应当知道索赔事件发生30天内向对方提出索赔意向通知书的，则丧失要求追加付款和延长工期的权利",true,{"key":20,"text":21,"correct":14},"C","为避免争议，《2013版施工合同》明确规定“逾期索赔失权制度”对发包人和承包人均适用",{"key":23,"text":24,"correct":14},"D","承包人提交的最终结清文件中，只限于提出工程竣工接收证书颁发后发生的任何索赔","B项，《2007版标准文件》建立了合同当事人逾期索赔失权的制度，即承包人未能在知道或应当知道索赔事件发生28天内向对方提出索赔意向通知书的，则丧失要求追加付款和延长工期的权利。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]