[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981675,710,1,"单选题","下列各项中，不属于采购变更范围的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因执行基准日期之后新颁布的法律、标准、规范引起的变更",false,{"key":16,"text":17,"correct":14},"B","发包人要求改变检查、检验、检测、试验的地点和增加的附加试验",{"key":19,"text":20,"correct":21},"C","对设备、材料、部件的性能、规格和数量的调整",true,{"key":23,"text":24,"correct":14},"D","发包人要求增减合同中约定的备品备件、专用工具、竣工后试验物资的采购数量","采购变更范围包括：①承包人已按发包人批准的名单，与相关供货商签订采购合同或已开始加工制造、供货、运输等，发包人通知承包人选择该名单中的另一家供货商；②因执行基准日期之后新颁布的法律、标准、规范引起的变更；③发包人要求改变检查、检验、检测、试验的地点和增加的附加试验；④发包人要求增减合同中约定的备品备件、专用工具、竣工后试验物资的采购数量；⑤上述变更所需的附加工作。C项属于设计变更范围。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]