[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981670":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981670,710,1,"单选题","下列关于设计合同价款与支付的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人和设计人应在合同协议书中选择单价合同和总价合同这两种合同价格形式中的一种",true,{"key":16,"text":17,"correct":18},"B","定金的比例不应超过合同总价款的20%",false,{"key":20,"text":21,"correct":18},"C","预付款的比例由发包人与设计人协商确定，一般不低于合同总价款的20%",{"key":23,"text":24,"correct":18},"D","在对已付进度款进行汇总和复核中发现错误、遗漏或重复的，发包人和设计人均有权提出修正申请","发包人和设计人应在合同协议书中选择下列一种合同价格形式：①单价合同；②总价合同；③其他价格形式。A项，发包人和设计人在合同协议书中也可以选择其他价格形式。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]