[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981664,710,1,"单选题","下列不属于勘察设计合同的变更表现的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察设计错误的修改",true,{"key":16,"text":17,"correct":18},"B","勘察设计进度计划的变动",false,{"key":20,"text":21,"correct":18},"C","勘察设计规范的改变",{"key":23,"text":24,"correct":18},"D","增加合同中约定的勘察设计工作量","勘察设计合同的变更表现为：①设计图纸和说明的非勘察设计错误的修改；②勘察设计进度计划的变动；③勘察设计规范的改变；④增减合同中约定的勘察设计工作量等。这些变更导致了合同双方的责任变化。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]