[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981663,710,1,"单选题","《工程总承包合同示范文本》适用于建设项目工程总承包的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承发包方式",true,{"key":16,"text":17,"correct":18},"B","DB方式",false,{"key":20,"text":21,"correct":18},"C","设计一施工方式",{"key":23,"text":24,"correct":18},"D","设计一采购一施工方式","《工程总承包合同示范文本》适用于建设项目工程总承包的承发包方式。在其条款设置中，将“技术与设计、工程物资、施工、竣工试验、工程接收、竣工后试验”等工程建设实施阶段相关工作内容分别作为独立条款，发包人可根据发包建设项目实施阶段的具体内容和要求，确定对相关建设实施阶段和工作内容的取舍。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]