[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981662,710,1,"单选题","在工程勘察设计合同的重点条款中，有关付费方式的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","《建设工程勘察合同示范文本（一）》约定，在合同生效后3天内，发包人应向勘察人支付勘察费的10%作为定金",true,{"key":16,"text":17,"correct":18},"B","《建设工程勘察合同示范文本（一）》约定，在提交勘察成果资料后10天内，发包人应一次付清剩余的全部勘察费",false,{"key":20,"text":21,"correct":18},"C","《建设工程勘察合同示范文本（二）》约定，可按具体的时间或实际工程进度，以合同规定的比例（以合同总额为基数）分多次支付工程进度款",{"key":23,"text":24,"correct":18},"D","因发包人对工程内容与技术要求提出变更时，除延误的工期需要顺延外，因变更导致勘察人的经济支出和损失应由发包人承担","A项，《建设工程勘察合同示范文本（一）》和《建设工程勘察合同示范文本（二）》均约定，在合同生效后3天内，发包人应向勘察人支付勘察费的20%作为定金。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]