[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981659,710,1,"单选题","()是建设工程施工合同的核心要素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":18},"B","质量",false,{"key":20,"text":21,"correct":18},"C","索赔",{"key":23,"text":24,"correct":18},"D","变更","在施工合同的时间管理中，对于建设工程施工合同，时间管理又称工期管理，工期是建设工程施工合同的核心要素。对于施工合同的履行，发包人和承包人应当从以下方面加强对合同工期的管理：①及时办理与开工有关的手续，确定实际开工与竣工时间；②及时确定施工组织设计方案，明确节点工期和施工过程的组织实施；③正确处理延期事件，确保工程按期竣工。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]