[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981648,710,1,"单选题","承包人应提前_____天将可以开始进行竣工试验的日期通知监理人，监理人应在该日期后_____天内，确定竣工试验具体时间。()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14;21",false,{"key":16,"text":17,"correct":14},"B","7;14",{"key":19,"text":20,"correct":21},"C","21;14",true,{"key":23,"text":24,"correct":14},"D","21;","承包人按照合同约定提交竣工文件、操作和维修手册后，进行竣工试验。承包人应提前21天将可以开始进行竣工试验的日期通知监理人，监理人应在该日期后14天内，确定竣工试验具体时间。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]