[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981647,710,1,"单选题","承接勘察任务或签订勘察合同时，工程应当具备()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","立项批准文件",true,{"key":16,"text":17,"correct":18},"B","勘察任务书",false,{"key":20,"text":21,"correct":18},"C","勘察许可批件",{"key":23,"text":24,"correct":18},"D","建筑总平面布置图","我国目前的基本建设程序主要包括项目建议书、可行性研究报告、立项审批、规划审批、勘察、设计、施工、验收和交付等阶段，各阶段有先后顺序关系。承接勘察任务或签订勘察合同时，工程应当具备立项批准文件，且该立项批准文件的批准文号和日期应当在勘察协议中注明。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]