[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981635,710,1,"单选题","下列不属于索赔报告的基本要求的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","必须说明索赔事件应当符合法律规定和合同约定，并列出证明资料",false,{"key":16,"text":17,"correct":14},"B","必须说明工期延误以及损失金额的具体明细以及依据",{"key":19,"text":20,"correct":21},"C","必须说明违约方的责任",true,{"key":23,"text":24,"correct":14},"D","说明事件与损失之间的因果关系、关联性，并附明依据资料","索赔报告的基本要求有：①必须说明索赔事件应当符合法律规定和合同约定，并列出证明资料。即基于何种事件、何种理由提出索赔请求。具体包括事件描述、影响描述、后果描述以及各部分的证明资料。②必须说明工期延误以及损失金额的具体明细以及依据。③说明前述事件与损失之间的因果关系、关联性，并附明依据资料。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]