[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981626,710,1,"单选题","专业分包人按照计量程序约定的时间向总承包人提交进度付款申请单后，总承包人应在收到专业分包人进度付款申请单后()天内完成审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","21",true,{"key":20,"text":21,"correct":14},"C","25",{"key":23,"text":24,"correct":14},"D","28","专业分包人按照计量程序约定的时间向总承包人提交进度付款申请单后，总承包人应在收到专业分包人进度付款申请单后21天内完成审核。除在专用合同条款另有约定外，总承包人应在收到专业分包人进度付款申请单后21天签发进度款支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]