[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981625,710,1,"单选题","专业分包人认为有权得到追加付款和（或）延长工期的，应在知道或应当知道索赔事件发生后()天内，向总承包人递交索赔意向通知书，并说明发生索赔事件的事由。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","28","关于索赔程序，可以在施工专业分包合同中规定详细的索赔流程，如专业分包人认为有权得到追加付款和（或）延长工期的，应在知道或应当知道索赔事件发生后14天内，向总承包人递交索赔意向通知书，并说明发生索赔事件的事由，在发出索赔意向通知书后14天内，向总承包人正式递交索赔报告，索赔事件影响结束后14天内，专业分包人应向总承包人递交最终索赔报告，总承包人应在收到索赔报告后14天内完成审查等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]