[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981622,710,1,"单选题","下列关于承包人的合理化建议的说法中，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在履行合同过程中，承包人对发包人要求的合理化建议，不一定均以书面形式提交监理人",true,{"key":16,"text":17,"correct":18},"B","合理化建议书的内容应包括建议工作的详细说明、进度计划和效益以及与其他工作的协调等",false,{"key":20,"text":21,"correct":18},"C","监理人应与发包人协商是否采纳建议",{"key":23,"text":24,"correct":18},"D","建议被采纳并构成变更的，应按照变更程序约定向承包人发出变更指示","在履行合同过程中，承包人对发包人要求的合理化建议，均应以书面形式提交监理人。合理化建议书的内容应包括建议工作的详细说明、进度计划和效益以及与其他工作的协调等，并附必要的设计文件。监理人应与发包人协商是否采纳建议。建议被采纳并构成变更的，应按照变更程序约定向承包人发出变更指示。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]