[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981621,710,1,"单选题","关于设计施工一体化，下列说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","如果工程出现质量缺陷，承包人将承担全部责任",false,{"key":16,"text":17,"correct":18},"B","如果工程出现质量缺陷，承包人只承担部分责任",true,{"key":20,"text":21,"correct":14},"C","有利于缩短建设周期",{"key":23,"text":24,"correct":14},"D","有利于降低工程造价","工程总承包合同的承包人不仅负责工程施工，还需负责合同约定范围内的设计与材料设备采购工作。因此，如果工程出现质量缺陷，承包人将承担全部责任，不会导致设计、施工等多方之间相互推卸责任的情况；同时设计与施工的深度交叉，有利于缩短建设周期，提高设计的可施工性，降低工程造价。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]