[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981616,710,1,"单选题","下列不属于合同总体需求分析的工作要点的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总体目标的确定",false,{"key":16,"text":17,"correct":14},"B","相关市场信息的调研",{"key":19,"text":20,"correct":21},"C","资金投放的决策",true,{"key":23,"text":24,"correct":14},"D","相关法律政策的调研","招标采购合同总体需求分析应当围绕工程建设项目或政府采购活动的总体需求展开。从工作流程及逻辑的角度而言，其工作要点包括：①总体目；标的确定；②基本信息的采集；③相关市场信息的调研；④相关法律政策的调研；⑤项目总体需求的分析；⑥合同总体需求的分析。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]