[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},981614,710,1,"单选题","工作分解结构可以从多种角度进行，其中不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按产品的物理结构分解",false,{"key":16,"text":17,"correct":18},"B","按最小合同单元分解",true,{"key":20,"text":21,"correct":14},"C","按照项目的实施过程分解",{"key":23,"text":24,"correct":14},"D","按照项目的地域分布分解","工作分解结构可以从多种角度进行，通常包括：①按产品的物理结构分解；②按产品或项目的功能分解；③按照项目的实施过程分解；④按照项目的地域分布分解；⑤按照项目的各个目标分解；⑥按建设单位的管理部门分解；⑦按实施主体的管理职能分解等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]