[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},981605,710,1,"单选题","招标采购合同履行与控制的主要内容不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同目标管理与激励",false,{"key":16,"text":17,"correct":14},"B","合同交底管理",{"key":19,"text":20,"correct":14},"C","合同重点要素管理",{"key":22,"text":23,"correct":24},"D","合同风险梳理",true,"招标采购合同履行与控制的主要内容包括：①合同目标管理与激励；②合同交底管理；③合同重点要素管理；④合同收尾；⑤合同跟踪与评价；⑥合同争议解决；⑦合同信息管理。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]