[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981602,710,1,"单选题","下列不属于合同目标管理的内容的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资总额控制管理",false,{"key":16,"text":17,"correct":14},"B","质量安全目标管理",{"key":19,"text":20,"correct":21},"C","价值管理",true,{"key":23,"text":24,"correct":14},"D","时间管理","合同目标管理应将合同整体目标逐级分解，转换为具体的权利义务，通过权利义务的实现达成合同目标，权利义务的设置应注意与招标采购人的项目目标管理相衔接，环环相扣，形成协调统一的权利义务体系。根据不同角度，合同目标管理可以分为：①投资总额控制管理；②质量安全目标管理；③时间管理等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]