[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981598,710,1,"单选题","下列关于项目管理方案与招标采购合同规划的表述不正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目管理方案应建立在对项目进行工作分解的基础上",false,{"key":16,"text":17,"correct":14},"B","招标采购合同规划应建立在对项目进行工作分解的基础上",{"key":19,"text":20,"correct":21},"C","招标采购合同规划是项目管理方案内容的基础条件",true,{"key":23,"text":24,"correct":14},"D","招标采购合同规划直接影响项目管理方案目标的实现","项目管理方案与招标采购合同规划既有联系又有区别：①项目管理方案和招标采购合同规划均应建立在对项目进行工作分解的基础上；②项目管理方案内容是招标采购合同规划的基础条件；③招标采购合同规划直接影响项目管理方案目标的实现。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]