[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},981591,710,1,"单选题","招标合同单元的确定直接或间接取决于()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","最小工作单元的分解",false,{"key":16,"text":17,"correct":14},"B","最小合同单元的确定",{"key":19,"text":20,"correct":14},"C","合同结构的分解",{"key":22,"text":23,"correct":24},"D","最小工作单元的分解和最小合同单元的确定",true,"合同结构分解的关键在于确定招标合同单元，而招标合同单元的确定直接或间接取决于最小工作单元的分解和最小合同单元的确定，故合同结构分解建立在整个项目工作分解的基础上。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]