[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},981589,710,1,"单选题","()是合同规划的首要工作，也是开启招标方案编制工作的基础工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","初步合同规划",true,{"key":16,"text":17,"correct":18},"B","工作分解",false,{"key":20,"text":21,"correct":18},"C","确定最小工作单元",{"key":23,"text":24,"correct":18},"D","确定招标合同单元","招标采购合同规划的过程应当围绕工程建设项目或政府采购项目的整体目标展开，并通过初步规划和工作分解，确定最小工作单元和最小合同单元，并最终经过招标优化分析，确定招标合同单元以实现合同标段划分。其中，初步合同规划是合同规划的首要工作，也是开启招标方案编制工作的基础工作，初步合同规划可以随着后续合同规划的深入而不断调整和完善。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]