[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},981556,710,1,"单选题","下列属于发包人可以不赔偿承包人损失的情形的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人改变项目建设方案的工程停建",false,{"key":16,"text":17,"correct":14},"B","征地拆迁工作不顺利导致施工现场移交延误",{"key":19,"text":20,"correct":21},"C","严重恶劣天气导致施工暂停",true,{"key":23,"text":24,"correct":14},"D","建设资金未能按计划到位的施工暂停","法定免责事由是指由法律直接规定、不需要当事人约定即可援用的免责事由，主要指不可抗力，即当事人订立合同时不能预见、不能避免和不能克服的自然灾害、战争等客观情况。不可抗力造成违约的，违约方一般不用承担责任，但法律规定因不可抗力造成的违约也要承担责任的除外。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购合同管理-(原案例分析)","建筑工程",0]