[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981532":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981532,709,2,"多选题","进行柱下条形基础的内力计算时，满足（ ）条件时可按连续梁计算，地基反力看作直线分布。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","上部结构刚度较小、地基土和荷载分布较不均匀",false,{"key":16,"text":17,"correct":18},"B","上部结构刚度较大、地基土和荷载分布都比较均匀",true,{"key":20,"text":21,"correct":14},"C","条形基础梁高度不大于柱距的1\u002F6",{"key":23,"text":24,"correct":18},"D","条形基础梁高度不小于柱距的1\u002F6","BD","条形基础梁的内力按连续梁计算的条件包括：当地基持力层土质均匀，上部结构刚度较好，各柱距相差不大(＜20%),柱荷载分布较均匀，且基础梁的高度大于1\u002F6 柱距时，地基反力认为符合直线分布，基础梁的内力可按简化的直线分布法计算。当不满足之前的条件，则按弹性地基梁法计算。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]