[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981481":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981481,709,2,"多选题","建设工程验收应具备的条件是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","完工",false,{"key":16,"text":17,"correct":18},"B","有完整的技术档案",true,{"key":20,"text":21,"correct":18},"C","有施工单位签署的工程保修书",{"key":23,"text":24,"correct":14},"D","有设计文件","BC","建设工程竣工验收应具备的条件有：①完成建设工程设计和合同约定的各项内容；②有完整的技术档案和施工管理资料；③有工程使用的主要建筑材料、建筑构配件和设备的进场试验报告；④有勘察、设计、施工、工程监理等单位分别签署的质量合格文件；⑤有施工单位签署的工程保修书。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]