[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981480":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981480,709,2,"多选题","建设工程勘察、设计单位不得将所承揽的建设工程勘察、设计转包。下列行为属于转包的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人将承包的全部建设工程勘察、设计转给其他单位或个人",true,{"key":16,"text":17,"correct":14},"B","承包人将承包的建设工程主体部分的勘察、设计转给其他单位完成",{"key":19,"text":20,"correct":14},"C","承包人将承包的全部建设工程勘察、设计肢解以后以分包的名义分别转给其他单位",{"key":22,"text":23,"correct":24},"D","将承包工程中的部分工程进行分包，但实行施工总承包的建筑工程主体结构的施工必须由总承包单位自行完成",false,"ABC","《建筑法》第二十八条的规定，禁止承包单位将其承包的全部建筑工程转包给他人，禁止承包单位将其承包的全部建筑工程肢解以后以分包的名义分别转包给他人。D项，施工总承包的，建筑工程主体结构的施工必须由总承包单位自行完成，因而属于合法分包。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]