[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981462":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981462,709,2,"多选题","其他直接费是指预算定额规定以外，现场施工中发生的或其他一些特殊情况所需具有直接费性质的费用。应归入其他直接费的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","检验试验费",true,{"key":16,"text":17,"correct":14},"B","材料二次搬运费",{"key":19,"text":20,"correct":14},"C","夜间施工增加费",{"key":22,"text":23,"correct":24},"D","施工使用机械大修费",false,"ABC","施工使用机械大修一般不会在现场的施工中发生，并非具有直接性质的费用，不应属于其他直接费。其他直接费包括：①夜间施工增加费；②冬、雨期施工增加费；③材料二次搬运费；④仪器、仪表使用费；⑤生产工具用具使用费；⑥检验试验费；⑦特殊工种培训费；⑧工程定位复测、工程点交、场地清理等费用；⑨特殊地区施工增加费。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]