[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981459":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981459,709,2,"多选题","岩土工程施工图预算与施工预算的差异是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制的目的及发挥的作用不同",true,{"key":16,"text":17,"correct":14},"B","采用的定额与内容不同",{"key":19,"text":20,"correct":21},"C","编制的步骤完全不同",false,{"key":23,"text":24,"correct":14},"D","采用的计算规则不同","ABD","岩土工程施工预算和施工图预算的差异是：①编制目的不同；②编制作用不同；③采用定额不同；④编制内容不同；⑤计算方法规则不同。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]