[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981414":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981414,709,2,"多选题","在湿陷性黄土地区建筑施工时，取土坑至建筑物外墙的距离根据《湿陷性黄土地区建筑 规范》（GB 50025-2004）应满足（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在非自重湿陷性黄土场地，不应小于12m",true,{"key":16,"text":17,"correct":18},"B","在非自重湿陷性黄土场地，不应小于25m",false,{"key":20,"text":21,"correct":18},"C","在自重湿陷性黄土场地，不应小于12m",{"key":23,"text":24,"correct":14},"D","在自重湿陷性黄土场地，不应小于25m","AD","取土坑至建筑物外墙的距离，在非自重湿陷性黄土场地，不应小于12m；在自重湿陷性黄土场地，不应小于25m。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]