[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981384":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981384,709,2,"多选题","泥石流地区的建筑适宜性评价中，下列说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","I1类泥石流沟谷不应作为建筑场地，各类线路工程应避开",false,{"key":16,"text":17,"correct":18},"B","II1类泥石流沟谷可以作为建筑场地",true,{"key":20,"text":21,"correct":14},"C","I2和II2类泥石流沟谷不宜作为建筑场地",{"key":23,"text":24,"correct":18},"D","当线路必须通过I2类泥石流沟口时，应设桥通过，桥位应设在河床弯曲处","BD","根据《岩土工程勘察规范》(GB 50021 -2001) （2009年版）第5. 4. 6条，泥石流地区工程建设适宜性的评价，应符合下列要求：①I1类和II2类泥石流沟谷不应作为工程场地，各类线路宜避开；②I2类和II2类泥石流沟谷不宜作为工程场地，当必须利用时应采取治理措施；线路应避免直穿堆积扇，可在沟口设桥（墩）通过；③I3类和II3类泥石流沟谷可利用其堆积区作为工程场地，但应避开沟口；线路可在堆积扇通过，可分段设桥和采取排洪、导流措施，不宜改沟、并沟；④当上游大量弃渣或进行工程建设，改变了原有供排平衡条件时，应重新判定产生新的泥石流的可能性。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]