[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981325":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981325,709,2,"多选题","设计某铁路通过软土场地，软土层厚度为2. 5m，表层无硬壳，软土呈流塑状态，工期较紧，该场地宜选用（ ）方法进行地基加固。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","换填法",true,{"key":16,"text":17,"correct":14},"B","拋石挤淤法",{"key":19,"text":20,"correct":21},"C","预压固结法",false,{"key":23,"text":24,"correct":21},"D","挤密砂桩或碎石粧法","AB","根据《建筑地基处理技术规范》（JGJ79 — 2002），软土厚度不深，工期较紧，可以直接换填或抛石。预压固结法需在地基处理前进行细致的现场检测试验，以所取得的监测资料指导地基处理工作的进行，因此对于工期较紧的场地不能够满足要求。挤密砂桩或碎石桩法适用于软土层厚度较深，持力层承载力相对较高的场地。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]