[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981319":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981319,709,2,"多选题","下述关于风砂地区的铁路路基设计错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风砂地区路基宜以高度不小于1.0m的路堤通过",false,{"key":16,"text":17,"correct":14},"B","风砂地区的粉细砂路基，应按非渗水土路基标准设计",{"key":19,"text":20,"correct":21},"C","当横向取弃土时，取土坑应设在迎风侧，且与路基坡脚不小于5m",true,{"key":23,"text":24,"correct":21},"D","线路两侧50m范围内的天然植被不得破坏","CD","当横向取弃土时，取土坑应设在背风侧坡脚5m以外。取土场（坑）的设置，应根据各地段取土性质、数量，并结合路基排水、地形、土质、施工方法、节约用地、 环保等要求，作出统一规划。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]