[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-981296":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},981296,709,2,"多选题","下列各项关于滑坡治理施工采用信息施工法应符合的要求不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","切坡严禁通长大断面开挖，必须采用自上而下分段跳槽的施工方式",true,{"key":16,"text":17,"correct":18},"B","应控制施工用水，切坡不宜在雨季实施",false,{"key":20,"text":21,"correct":14},"C","滑坡治理施工可采用普通爆破法",{"key":23,"text":24,"correct":18},"D","各单项治理工程的施工程序应有利于施工期滑坡稳定和治理","AC","在实际工程中，若滑坡治理施工采用信息施工法，那么切坡不宜在雨季实施；应控制施工用水，切坡严禁通长大断面开挖，必须采用自下而上分段跳槽的施工方式；各单项治理工程的施工程序应有利于施工期滑坡稳定和治理；滑坡治理施工宜采用特殊爆破施工法。",{"id":6,"name":28,"category":29,"favorite":30},"岩土专业知识","建筑工程",0]